Thank you for reporting this event (OM2017-047) to the National Energy Board. This message confirms that you have completed your submission to the NEB of all information for this event as listed below. Your contact at the NEB will review all of the material. If any clarification is required, you will be contacted for more information; otherwise, the NEB will close its file for this event. Please note that you will no longer be able to use the link provided previously for access to the online event reporting system. To revise any of the data or provide further information, please contact the NEB at dlerssupport@neb-one.gc.ca.
Following is a list of the data that you have provided to the NEB:
TNPI plans on installing river-stone rip rap as a temporary depth of cover remediation for the exposed pipe at milepost 34.8. This installation will be completed before March 31st, 2017.
To temporarily provide adequate cover for the pipe before the weather thaws. To have this cover in place before the end of the timing window for carrying out work in fish habitat for the project location (August 1 to March 31). The inclusion of riprap into the channel bed and bank would act to increase channel roughness and therefore decrease flow velocities and erosive stress. This should provide cover until a permanent solution can be decided upon and implemented.
Ground disturbance using power-operated equipment within 30 m of a wetland or a water body, or within 30 m of the substrate of a wetland or water body
TNPI has been in consultation with the National Energy Board and have been providing frequent status updates for this project. TNPI through Stantec have consulted with the MDDELCC in Quebec, from whom we are in the process of obtaining a CofA for this work. TNPI have also been in contact with landowners, and the Ville de Saint-Lazare and the Municipalite Regionale de Vaudreuil Soulanges.
Between Chemin St-Louis and Route Harwood along the TNPI Right-of-Way.
Activity Coordinates
Latitude
Longitude
45.41404900
-74.11708200
Company
Trans-Northern Pipelines Inc.
Select all regulations that apply to this event. (Note that different acts may apply depending on the selected company.)
Not specified
Water Body
Yes
1
Yes
Yes
Yes
Yes
Yes
No
No
Not specified
Not specified
Documents (5)
Environmental Practices Manual
Final Rip Rap Design (See Option 1)
Temporary Solution Plan
Temporary Solution Profile
OM2017-047 - Final Submission
This is an automated email sent from the National Energy Board (NEB).
If clicking on a link in this message does not work, copy the complete link text and paste it into the address line of your browser.
Do not reply directly to this message as it comes from an account which is not monitored.
If you encounter problems of any kind in using this system, please contact the NEB at dlerssupport@neb-one.gc.ca for assistance.