Compliance Verification Activity Report: CV1819-299 - Westcoast Energy Inc., carrying on business as Spectra Energy Transmission

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1819-299
Start date: 2018-05-07
End date: 2018-05-07

Team:

Regulated company: Westcoast Energy Inc., carrying on business as Spectra Energy Transmission

Operating company: Westcoast Energy Inc. carrying on business as Spectra Energy Transmission

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

Assess compliance with the OPR, CLC and company-specific program requirements with respect to safety at Rosedale CS9 upgrade and rebuild.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - Compressor Station Upgrade/Rebuild Construction

Date & time of visit: 2018-05-07 15:00

Discipline: Safety Management

Categories:

Facility:

Observations:


 

Compliance tool used: No compliance tool used

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program