Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Trans Mountain Pipeline ULC
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
Construction inspection of the Trans Mountain Pipeline Expansion Project. Westridge Terminal, Burnaby Terminal and Sumas Pump Station. Focus was on contractor management activities, site-specific hazards identified in the construction safety manuals and in-water safety measures.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Burnaby Storage Tank Facility- General Observations
Date & time of visit: 2018-01-10 08:00
Discipline: Safety Management
Categories:
Facility:
Observations:
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
No further action required for the damaged sling but an IR has been sent to identify the process for slings and rigging equipment.
Due date: 2018-01-10
Date closed: 2018-01-10 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 2 - Westridge Marine Terminal - General Observations
Date & time of visit: 2018-01-10 14:00
Compliance tool used: No compliance tool used
Observation 3 - Sumas Pump Station - General Comments
Date & time of visit: 2018-01-11 12:00
Observation 4 - Information Request
Date & time of visit: 2018-01-11 15:00
We request that TransMountain provide a response to the following questions pertaining to the Westridge Marine Terminal:
Compliance tool used: Information Request (IR)
Please respond to the Information Request by 8 Feb, 2018.
Due date: 2018-02-08
Date closed: 2018-02-16 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
There are no observations with outstanding follow-up
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program
Observation 5 - Information caviardée conformément au paragraphe 144(5) du Code canadien du travail
This information has been redacted pursuant to Section 144(5) of the Canada Labour Code