Compliance verification activity type: Field Inspection
Team:
Regulated company: ARC Resources Ltd.
Operating company: ARC Resources Ltd.
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
Verify Damage Prevention program implementation through field inspection in on the AB/BC border north of Dawson Creek BC.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - Damage Prevention Program
Date & time of visit: 2016-06-22 09:32
Discipline: Damage Prevention
Categories:
Facility:
Observations:
Damage Prevention Program:
Compliance tool used: No compliance tool used
Observation 2 - 2. ARC Resources Pipeline
Date & time of visit: 2016-06-22 10:25
NEB inspectors accompanied ARC company staff to several sites along the ROW, approximately 38.2 km in length.
Observation 3 - 3. ARC Riser 16-31-79-13 W
Date & time of visit: 2016-06-22 11:15
NEB Inspectors observed a riser and RoW with signage located at appropriate locations and was free and clear from vegetation. Both observations were compliant with CSA Z662 10.5.3.3 in regards to signage and vegetation under CSA Z662-15 10.6.2.
Observation 4 - Crossing at Sweet Road near Rolla BC
Date & time of visit: 2016-06-22 11:25
NEB Inspectors noticed appropriate signage and free from brush at crossing where 2 inch field gas, 6 inch raw gas line, and a 10 inch sales line.Both observations were compliant with CSA Z662 10.5.3.3 in regards to signage and vegetation under CSA Z662-15 10.6.2.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program