Compliance verification activity type: Field Inspection
Team:
Regulated company: Genesis Pipeline (Canada) Ltd.
Operating company: Nova Chemicals Corporation
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Damage Prevention Right-of-Way inspection of the Genesis Pipeline (Canada) Ltd. in Sarnia, Ontario to ensure compliance with the National Energy Boards legislative requirements, including the Damage Prevention Regulations and Onshore Pipeline Regulations.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Damage Prevention Right-of-Way inspection of the Genesis Pipeline (Canada) Ltd. to ensure compliance with the National Energy Boards regulatory requirements
Date & time of visit: 2017-05-09 13:00
Discipline: Damage Prevention
Categories:
Facility:
Observations:
NEB staff observed three pipeline identification/warning signs at the same location. Two signs were in compliance but NEB inspectors noted that one sign did not indicate the area code with the emergency number. This is in contravention to CSA Z662-15. s.10.5.3.3 (c).Inspectors also note that this is a repeat finding, as this was identified at another location on the Genesis Pipeline RoW during an inspection conducted in 2010 in the same geographical area.
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Sign is to be corrected to comply with the Onshore Pipeline Regulations (OPR) 4 (1) (d) and CSA Z662-15 10.5.3.3 (c)OPR 4 (1) When a company designs, constructs, operates or abandons a pipeline, or contracts for the provision of those services, the company shall ensure that the pipeline is designed, constructed, operated or abandoned in accordance with the applicable provisions of(d) CSA Z662, if the pipeline transports liquid or gaseous hydrocarbons;CSA Z662-15 10.5.3.3(c) the name of the operating company and emergency notification information, including an emergency telephone number with area code.
Due date: 2017-05-10
Date closed: 2017-05-10 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 2 - Damage Prevention Right-of-Way inspection of the Genesis Pipeline (Canada) Ltd. to ensure compliance with the National Energy Boards regulatory requirements
Genesis Pipeline (Canada) Ltd. is owned and operated by Nova Chemical (Canada) Limited. NEB staff conducted a Compliance Screening meeting the morning of May 9th, 2017 with Nova Chemicals and interviews and documents reviewed informed the right-of-way inspection. The following list outlines some of the documents reviewed and information provided during the meeting:
Compliance tool used: No compliance tool used
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program