Compliance Verification Activity Report: CV1617-445 - Plains Midstream Canada ULC

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1617-445
Start date: 2016-09-21
End date: 2016-09-21

Team:

Regulated company: Plains Midstream Canada ULC

Operating company: Plains Midstream Canada ULC (Plains)

Province(s) / Territory(s):

Discipline(s):

Rationale and scope:

Following a large spill at of a provincially regulated oil pipeline in Saskatchewan at the North Saskatchewan River, the NEB is conducting multi-discipline inspections of liquid pipelines crossing the South Saskatchewan River and Wascana Creek. These inspections are in addition to previously planned inspections in Saskatchewan, and focus specifically on compliance to Damage Prevention, Integrity, and Environmental requirements at watercourse crossings with participation from the Provincial Regulator. Specifically, the scope of this inspection was limited to the general RoW near the Wascana Pipeline crosses Wascana Creek.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - Safety - General

Date & time of visit: 2016-09-21 10:30

Discipline: Safety Management

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 2 - General - Environment

Date & time of visit: 2016-09-21 10:30

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 3 - General Damage Prevention

Date & time of visit: 2016-09-21 10:30

Discipline: Damage Prevention

Categories:

Facility:

Observations:



 
 

Compliance tool used: No compliance tool used

Observation 4 - General - Integrity

Date & time of visit: 2016-09-21 10:30

Discipline: Integrity Management

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program