Compliance Verification Activity Report: CV1617-328 - Whitecap Resources Inc.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1617-328
Start date: 2016-07-06
End date: 2016-07-06

Team:

Regulated company: Whitecap Resources Inc.

Operating company: Whitecap Resources Inc.

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

An environmental information exchange meeting was held in December 2015 to inform the company of the NEB's expectations. An operations inspection of the Boundary Lake 8" Fresh Water Injection Pipeline and 10" Oil Effluent Pipeline will verify that Whitecap is meeting environmental requirements.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Regulatory instrument number(s):

Observations (no outstanding follow-up required)

Observation 1 - Fresh Water Booster Station (16-26-84-14 W6M; Fresh Water Pipeline origin)

Date & time of visit: 2016-07-06 09:48

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 2 - RoW walking approx. 200 m east from Fresh Water Booster Station

Date & time of visit: 2016-07-06 10:04

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 3 - 14-25 Access Road Crossing

Date & time of visit: 2016-07-06 10:27

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 4 - 14-25 Access Road Crossing

Date & time of visit: 2016-07-06 10:35

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 5 - 16-25 Access Road Crossing

Date & time of visit: 2016-07-06 10:45

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 6 - 16-25 Access Road Crossing

Date & time of visit: 2016-07-06 10:50

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 7 - 14-30 Access Road Crossing

Date & time of visit: 2016-07-06 10:57

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 8 - 14-30 Access Road Crossing

Date & time of visit: 2016-07-06 11:01

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 9 - 14-29 Access Road Crossing

Date & time of visit: 2016-07-06 11:14

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 10 - Highway 64 Crossing, just west of AB/BC Border

Date & time of visit: 2016-07-06 11:29

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 11 - 08-32 Access Road Crossing

Date & time of visit: 2016-07-06 11:50

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 12 - Boundary Lake Battery 08-02 (08-02-085-14 W6M, Effluent Pipeline origin)

Date & time of visit: 2016-07-06 12:58

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 13 - Road 207 Crossing, Private Agricultural Land

Date & time of visit: 2016-07-06 13:10

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 14 - Boundary Creek Crossing

Date & time of visit: 2016-07-06 13:25

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 15 - Boundary Creek Crossing

Date & time of visit: 2016-07-06 13:31

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 16 - RoW between Airport Road crossing and wetland south of Boundary Lake, including Intersection with Provincial Line (per GPS coordinates)

Date & time of visit: 2016-07-06 13:43

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 17 - RoW between Airport Road crossing and wetland south of Boundary Lake, including Intersection with Provincial Line (per GPS coordinates)

Date & time of visit: 2016-07-06 13:45

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 18 - Shared RoW in AB (1) either side of BP 14-28 Access Road (to wetland south of Boundary Lake to NW, then continuing SE down RoW)

Date & time of visit: 2016-07-06 14:08

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 19 - Shared RoW in AB (2) BP 14-28 Access Road to Range Road 132

Date & time of visit: 2016-07-06 14:35

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 20 - Shared RoW in AB (3) Range Road 132 to Highway 64

Date & time of visit: 2016-07-06 14:49

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 21 - Boundary Lake Satellite & Pump Station / 03-23 Station L ESD Valve (03-23-84-13 W6M; Effluent Pipeline Origin and Fresh Water Pipeline Terminus)

Date & time of visit: 2016-07-06 15:06

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 22 - Environmental Management Manual

Date & time of visit: 2016-07-06 16:12

Discipline: Environmental Protection

Categories:

Facility:

Observations:

The company provided the NEB with a copy of their Environmental Management Manual, June 2012, and explained that they are currently producing a new integrated Environment, Health, Safety, and Security Manual which should be completed by the end of July 2016. The pipelines are also managed in accordance with the Whitecap Resources Inc. (NEB Pipelines) Pipeline Integrity Management Program, 2016 Edition (last updated 2016-04).

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Whitecap will provide NEB staff with an electronic copy of its new Environment, Health, Safety, and Security Manual via email upon completion.

Environmental Protection section (section 13) of HSE Management Manual dated August 2016 was provided to NEB staff on 15 Sept 2016, no further concerns.

Due date: 2016-09-15

Date closed: 2016-09-16
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program