Compliance Verification Activity Report: CV1617-096 - Foothills Pipe Lines Ltd.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1617-096
Start date: 2016-08-02
End date: 2016-08-05

Team:

Regulated company: Foothills Pipe Lines Ltd.

Operating company: TransCanada PipeLines Limited

Province(s) / Territory(s):

Discipline(s):

Rationale and scope:

Operations environmental inspection of the South BC - Zone 8 pipeline right-of-way (RoW) between Fernie and Moyie BC areas.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - Information Request #1

Date & time of visit: 2016-08-02 12:25

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Inspection Officers submitted the following Information Request (IR) via email following the opening meeting.

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Please provide the following information:

Due date: 2016-08-08

Date closed: 2016-08-25
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 2 - KP 0+3 XR-001 AB/BC Border - Crossover Valve

Date & time of visit: 2016-08-02 12:27

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 3 - CNC #1: KP 0+3 XR-001 AB/BC Border - Crossover Valve

Date & time of visit: 2016-08-02 14:27

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Site is a few hundred meters within AB border, discussed that weed control is responsibility of AB operator. Some mullein, oxeye daisy within facility fenceline, vegetation not managed within facility or outside of the perimeter fence. 

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TransCanada shall ensure that weed management is conducted at the KP 0+3 crossover valve site and send photo(s) upon completion.

Due date: 2016-08-05

Date closed: 2016-08-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 4 - CNC #2: KP 0+3 XR-001 AB/BC Border - Crossover Valve

Date & time of visit: 2016-08-02 14:27

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Personal protective equipment (PPE) requirements are missing from facility signage.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TransCanada shall install PPE requirements signage on the facility fencing and submit photo(s) upon completion.

Due date: 2016-08-05

Date closed: 2016-08-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 5 - KP 3+73 Summit Creek Crossing

Date & time of visit: 2016-08-02 15:06

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 6 - Information Request #2

Date & time of visit: 2016-08-02 15:06

Discipline: Environmental Protection

Categories:

Facility:

Observations:

A rusted steel grate possibly from a historic train derailment was resting on the creek banks. A company representative stated that they would consult with a biologist on possible disturbance caused by removal of the grate. 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Please submit a copy of the email response from the biologist regarding possible disturbance cause by removal of the grate from the creek.

Due date: 2016-10-14

Date closed: 2016-10-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 7 - CNC #3: Power Plant Road Crossing

Date & time of visit: 2016-08-02 15:42

Discipline: Damage Prevention

Categories:

Facility:

Observations:

A Foothills Mainline sign was down on the SW side of the road crossing, the TransCanada sign was on both sides of the crossing. A company representative stated that there is a work order to conduct RoW maintenance, including signage repairs/replacements.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TransCanada shall repair the Foothills Mainline signage and submit a photo to NEB staff upon completion.

Due date: 2016-08-05

Date closed: 2016-08-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 8 - KP 8+0 Other Side of Hill from Sparwood Tap

Date & time of visit: 2016-08-02 16:20

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 9 - Information Request #3

Date & time of visit: 2016-08-03 08:50

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Following an overview of the 2016 B.C. Summer Dig Program, company representative stated that sites were reseeded using a low elevation or a high elevation seed mix.

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Please submit the Certificate of Analysis for the low elevation seed mix.

Due date: 2016-09-02

Date closed: 2016-08-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 10 - KP 15+3 MLV Site 1-0a

Date & time of visit: 2016-08-03 09:59

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 11 - KP 18+2 Inlet to Byron Creek Meter Station

Date & time of visit: 2016-08-03 11:06

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 12 - KP 17+3 Carbon Creek Crossing

Date & time of visit: 2016-08-03 11:25

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 13 - KP 19+2 Leach Creek Crossing

Date & time of visit: 2016-08-03 12:15

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 14 - GWD 24710 Integrity Dig Site

Date & time of visit: 2016-08-03 12:24

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 15 - Information Request #4

Date & time of visit: 2016-08-03 12:24

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Inspection Officers noted water bars approximately 1 m width and 0.3 m high along the bank of the drainage ditch at the GWD 24710 integrity dig site.

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Please submit a copy of the pre-activity report (including photos taken prior to ground disturbance) to Inspection Officers for the GWD 24710 dig site.

Due date: 2016-08-08

Date closed: 2016-08-08
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 16 - KP 24+4 Valve Station

Date & time of visit: 2016-08-03 12:53

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 17 - KP 32+0

Date & time of visit: 2016-08-03 15:48

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 18 - GWD 20600 Integrity Dig Site

Date & time of visit: 2016-08-03 16:08

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 19 - CNC #4: GWD 20600 Integrity Dig Site

Date & time of visit: 2016-08-03 14:08

Discipline: Environmental Protection

Categories:

Facility:

Observations:

No separation observed between topsoil and subsoil piles on the east side of the excavation due to narrow area/lack of space for excavator, and no sediment fence or other barrier separated the soil piles.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TransCanada shall install a sediment fence or other appropriate barrier between the topsoil and subsoil piles.

Due date: 2016-08-04

Date closed: 2016-08-04
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 20 - KP 40+2 Morrissey Creek Crossing

Date & time of visit: 2016-08-03 16:47

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 21 - GWD 31120 Integrity Dig Site

Date & time of visit: 2016-08-03 17:08

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 22 - CNC #5: GWD 31120 Integrity Dig Site

Date & time of visit: 2016-08-03 17:08

Discipline: Environmental Protection

Categories:

Facility:

Observations:

At the base of the hill where the excavation took place was a temporary access bridge (constructed from rig mats) over an unnamed tributary to the Flathead River. The sediment fence barriers at the corners of the bridge had failed, allowing sediment from the road to flow into the creek from all sides.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TransCanada will repair the sediment fence barriers and remove as much sediment as practicable from the creek.

Due date: 2016-08-05

Date closed: 2016-08-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 23 - KP 53+7 Fernie Sales Meter Station

Date & time of visit: 2016-08-04 08:42

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 24 - KP 49+5

Date & time of visit: 2016-08-04 10:01

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 25 - KP 48+0 Valve Site

Date & time of visit: 2016-08-04 10:34

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 26 - KP 46+5

Date & time of visit: 2016-08-04 11:04

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 27 - KP 51+0

Date & time of visit: 2016-08-04 11:56

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 28 - Mount Broadwood Erosion Repair

Date & time of visit: 2016-08-04 13:13

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 29 - KP 59+0 (Approximate)

Date & time of visit: 2016-08-04 14:08

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 30 - Upstream Plot Plan

Date & time of visit: 2016-08-04 14:51

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 31 - KP 69+4 Elk River Crossing

Date & time of visit: 2016-08-04 15:34

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 32 - KP 131+0 GWD 30080 Integrity Dig Site

Date & time of visit: 2016-08-05 09:15

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 33 - CNC #6: KP 131+0 GWD 30080 Integrity Dig Site

Date & time of visit: 2016-08-05 09:15

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Observed approximately 10 m of an old sediment fence within the riparian area of Stone Creek that had been left in the ground from previous work (likely from the 1991 dug-out).

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TransCanada will remove the sediment fence and dispose of it appropriately. 

Due date: 2016-08-05

Date closed: 2016-08-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 34 - NNC #1: Missing/Damaged Pipeline Identification Signage

Date & time of visit: 2016-08-05 10:45

Discipline: Damage Prevention

Categories:

Facility:

Observations:

KP 17+3 Carbon Creek Crossing and KP 18+9:

KP 54+4 Logging/Heavy Equipment Road Crossing:
  • One sign was knocked down and another sign was missing from this crossing.
KP 131+0 GWD 30080 Integrity Dig Site

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Replace all missing or damaged signage at identified locations as per TransCanada's Pipeline Right Of Way Procedure, and provide photos of each location to NEB staff upon completion.

Due date: 2016-09-30

Date closed: 2016-10-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 35 - Information Request #5

Date & time of visit: 2016-08-05 10:45

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Several areas along the RoW were observed to have noxious weed infestations. The company representatives stated that these sites were scheduled to undergo weed spraying in the fall of 2016. Most of the impacted areas were confirmed through Information Request #1 to have been included in the 2016 Notice of Intent to Treat, however Inspection Officers would like to confirm that the following locations have been included for treatment as well: KP 53+7 Fernie Sales Meter Station surrounding RoW (oxeye daisy, scentless chamomile, mullein, Canada thistle, common tansy), KP 48+0 Valve Site surrounding RoW (primarily oxeye daisy), and KP 51+0 (primarily oxeye daisy, Canada thistle, and mullein observed). 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Please submit the Herbicide Use Sheets for the above-noted locations after weed spraying has been completed.

Due date: 2016-09-30

Date closed: 2016-10-13
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 36 - Information Request #6

Date & time of visit: 2016-08-05 10:45

Discipline: Damage Prevention

Categories:

Facility:

Observations:

At the following locations signage was observed to be missing or in disrepair (possibly due to ongoing construction), a company representative stated that the signage will be replaced once work has been completed:

GWD 24710 Integrity Dig Site:

KP 40+2 Morrissey Creek Crossing:GWD 31120 Integrity Dig Site:

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Please submit photos of replaced signage at the above-identified locations to NEB staff upon completion.

Due date: 2016-09-30

Date closed: 2016-10-14
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program