Compliance Verification Activity Report: CV1718-252 - Enbridge Pipelines Inc.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1718-252
Start date: 2017-10-02
End date: 2017-10-05

Team:

Regulated company: Enbridge Pipelines Inc.

Operating company: Enbridge Pipelines Inc.

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

Planned construction inspection of the Line 3 Replacement Program, specifically, Spread 1. Focus on Contractor Management program, assess compliance with the NEB Onshore Pipeline regulations, site-specific hazards identified in the Construction Safety Manuals, pipe-handling, and any potential high risk activities. Include two pump stations, Metiskow and Cactus Lake.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Regulatory instrument number(s):

Observations (no outstanding follow-up required)

Observation 1 - Metiskow Pump Station

Date & time of visit: 2017-10-03 10:30

Discipline: Safety Management

Categories:

Facility:

Observations:

Tuesday, October 3rd Enbridge Line 3RP (S.E. 1/4 1 40 5 W4M)

Compliance tool used: No compliance tool used

Observation 2 - Cactus Lake Pump Station

Date & time of visit: 2017-10-03 15:45

Discipline: Safety Management

Categories:

Facility:

Observations:

Tuesday, October 3rd Enbridge Line 3RP (Lat. 52.1410 Long. -109.8133  K.P. 180.13)

Compliance tool used: No compliance tool used

There are no observations with outstanding follow-up

Observation 3 - Provost Stock Pile- Pipe Line Yard

Date & time of visit: 2017-10-05 08:05

Discipline: Safety Management

Categories:

Facility:

Observations:

O.J. Pipelines Provost Pipeline Stock Yard

Compliance tool used: No compliance tool used

Observation 4 - Lowering 36" Pipe and Coating "Jeeping"

Date & time of visit: 2017-10-04 09:55

Discipline: Safety Management

Categories:

Facility:

Observations:

Construction Chainage> 10+229.5 Lowering Pipe

Compliance tool used: No compliance tool used

There are no observations with outstanding follow-up

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program

Observation 5 - Information caviardée conformément au paragraphe 144(5) du Code canadien du travail

This information has been redacted pursuant to Section 144(5) of the Canada Labour Code

Observation 6 - Information caviardée conformément au paragraphe 144(5) du Code canadien du travail

This information has been redacted pursuant to Section 144(5) of the Canada Labour Code