Compliance verification activity type: Field Inspection
Team:
Regulated company: Enbridge Pipelines Inc.
Operating company: Enbridge Pipelines Inc.
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Spread 6: Follow up on recent series of reported injuries and incidents on Enbridge Line 3 construction.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - General
Date & time of visit: 2018-12-08 06:00
Discipline: Safety Management
Categories:
Facility:
Observations:
Compliance tool used: No compliance tool used
Observation 2 - Bending Machine
Date & time of visit: 2018-12-08 09:14
Observation 3 - Road Crossing - Horizontal Directional Bore(HDB) and Hydrovac
Date & time of visit: 2018-12-08 11:00
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program